On Thursday the 11th April IMP Crinum crews laid 125 cubic metres of concrete in the MG 25 travel road in 1 x 12 hour shift.

The crews led by Berto and Rob Snape worked well together and are starting to perfect the methodology of Concreting roadways via pumping the concretre Underground. This pour was started at 4 c/t and worked out bye till the end of shift and they believe that the modifications to the screed have worked well.

As IMP perfect the pumping methodology we hope to be able to pump further into the UG with the ultimate goal to reach 800 metres.